Short answers from our daily site work. Each answer is one sentence, followed by what we do at Easy Smart Est. (السهل الذكي) in Dammam, Khobar, Dhahran and Qatif.

Questions
Plumbing

How is plumbing checked before plastering?

The water network is tested with water before the wall covers it and a test report is written, and the pipes, joints and clamps are photographed while exposed. Plastering starts after that.

At Easy Smart Est. we close plumbing stages with a test report, in Dammam, Khobar, Dhahran and Qatif.

Plumbing

Why is underground drainage photographed before backfill?

Because the route, joints and falls of underground drainage cannot be seen after backfill, and the photo stays as a record if the consultant asks or a problem appears after the work is covered.

At Easy Smart Est. we water-test the drainage and photograph it while it is open, before backfill, and the photos go into the stage record, in Dammam, Khobar, Dhahran and Qatif.

Plumbing

Why does a drain sometimes block after the family moves in?

One cause is a drain branch that joins at a right angle against the direction of flow instead of at an angle with it. The mistake does not show until the wall is covered, and fixing it means breaking the finish.

At Easy Smart Est. we photograph drain joints and their falls before they are covered, and the photo stays as a record, in Dammam, Khobar, Dhahran and Qatif.

Plumbing

What happens to leftover plumbing materials at the end of a stage?

They are counted on site piece by piece, by item, size, quantity and condition, and written into an inventory record that both sides sign on site, each keeping a copy.

At Easy Smart Est. every stage is documented, including what is left over, in Dammam, Khobar, Dhahran and Qatif.

Electrical

What should I receive from the electrician at handover?

You should receive a circuit schedule, a label on every breaker in the panel saying what it feeds, and photos of the conduit routes and boxes taken before they were covered.

At Easy Smart Est. we photograph the routes and boxes before plastering, and the photos reach you in the daily report, in Dammam, Khobar, Dhahran and Qatif.

Electrical

What colour is the earth wire in an electrical box?

Under the Saudi Building Code the earth wire is green and yellow, neutral is blue, and the phase in a single-phase circuit is brown; in a three-phase circuit the phases are brown, black and grey.

At Easy Smart Est. we test and record the earthing before the wiring is covered, in Dammam, Khobar, Dhahran and Qatif.

Source: Saudi Building Code SBC 401 (2024), clause 51-4-2

Electrical

What should I ask the electrician before the walls are closed?

Three questions: were the routes and boxes photographed, were the loads measured and compared with the design, and was the earthing tested and recorded?

At Easy Smart Est. we document the routes and the earthing with photos before plastering, in Dammam, Khobar, Dhahran and Qatif.

Electrical

Who calculates the electrical loads of a villa?

The design engineer calculates the loads in the design; on site, the contractor measures and compares the installation with the design before the walls are closed.

At Easy Smart Est. we build to the engineering office's drawings, and we measure and compare on site, in Dammam, Khobar, Dhahran and Qatif.

Electrical

When should I decide where sockets and switches go?

Before plastering, during the conduit stage, because moving a socket or switch after plastering means breaking and patching the wall.

At Easy Smart Est. we mark the box positions on the wall and photograph them before plastering, in Dammam, Khobar, Dhahran and Qatif.

Plastering

How long should plaster be kept damp after each coat?

Cement plaster goes on in at least two coats over blockwork, and each coat is sprayed and kept damp for at least 24 hours indoors and at least 48 hours outdoors. This is the curing time, not the interval between coats; a smooth surface needs a bonding coat first.

At Easy Smart Est. we photograph the wall before it is plastered, and the photo stays as a record, in Dammam, Khobar, Dhahran and Qatif.

Source: Saudi Building Code SBC 1101 (2024), clauses 8A2.2.2.1 and 8A3.5.4; SBC 201 (2024), clause 2510.7

Plastering

How do I accept a plastered wall?

With a straightedge, not by eye: the straightedge is placed on the wall vertically, horizontally and diagonally, and any gap under it shows the wall is not flat. Accept it before painting, because fixing it afterwards is harder.

At Easy Smart Est. we accept the wall with a straightedge before painting, and we photograph it before it is covered, in Dammam, Khobar, Dhahran and Qatif.

Gypsum

When is a gypsum ceiling closed?

A gypsum ceiling is closed only after everything above it is checked and photographed while it is still open: electrical conduits and boxes, water pipes, and the sprinkler network if there is one.

At Easy Smart Est. we photograph the services while the ceiling is still open, on villas in Dammam, Khobar, Dhahran and Qatif.

Fire systems

Are fire sprinklers required in a villa?

In residential villas, automatic sprinklers are permitted but not required under the Saudi Building Code, and anyone who wants them should decide before the ceilings are built.

At Easy Smart Est. we supply and install firefighting systems to the approved drawings; we do not design them. We work in Dammam, Khobar, Dhahran and Qatif.

Source: Saudi Residential Building Code SBC 1101 (2024), clauses 313.1 and 313.1.1

Fire systems

Why does the smoke detector go off every time we cook?

Often the cause is the detector's position or type, not a fault: the standard the code refers to sets a distance between smoke detectors and cooking appliances, and where a smoke detector does not suit the space the code allows a heat detector. Do not disconnect the detector because it is annoying.

At Easy Smart Est. we install detectors to the approved drawings and test them before handover, in Dammam, Khobar, Dhahran and Qatif.

Source: SBC 1101 clause 314.1 and SBC 801 clause 907.4.3 (2024); NFPA 72 (2022) clause 29.11.3.4

Before you start

How does a stage close at Easy Smart Est., and when is it paid?

A stage does not end with "we're done": it is tested, a test report is written, the handover record is signed, and then the claim comes as a numbered letter with both records and the invoice, and your payments are tied to the contract stages.

This is how Easy Smart Est. works with owners, contractors and developers, in Dammam, Khobar, Dhahran and Qatif.

Before you start

Does Easy Smart Est. work as a subcontractor for contractors and developers?

Yes. Easy Smart Est. (السهل الذكي) works for owners directly and as a subcontractor for contractors and developers in plumbing, electrical, fire alarm, firefighting, building, plastering and gypsum.

Every stage reaches you with its file: photos before covering, a written contract and a handover record, and repeat villas get the same contract and the same stage record, in Dammam, Khobar, Dhahran and Qatif.

Before you start

What is Easy Smart Est. and what does it do?

Easy Smart Est. (السهل الذكي) is a contractor in Saudi Arabia's Eastern Province, based in Khobar, doing seven activities from one team: building, plastering, plumbing, electrical, gypsum, fire alarm systems and firefighting systems, for villas, buildings, shops and warehouses.

Nothing is closed until you have seen it and received it with a handover record, and your payments are tied to the contract stages. We work in Dammam, Khobar, Dhahran and Qatif. Easy dealing | Smart execution.

We can help

Have a question about your site?

We serve Dammam, Khobar, Dhahran and Qatif. Send us your question or photos of the site and we'll reply.

Our seven activities

  • Building, plastering and gypsum
  • Plumbing and electrical
  • Fire alarm and firefighting
Service details →
Related questions